Respect state interests in National Interest Electric Transmission Corridors

Partially done

Printed page 406 12. Department of Energy and Related Commissions

“With respect to NIETCs, FERC and the new DESAS should ensure that state interests are respected and not allow such NEITC transmission lines to be developed as a mere subsidy to renewable developers.”

What has happened

  1. Partially done

    DOE canceled the three proposed National Interest Electric Transmission Corridors selected in December 2024, saying the process should not continue and citing public feedback, local community concern about the scope of NIETC authority, and a climate-alarmist agenda rather than reliability or cost. That is the state and local interest the Quote asks be respected, given effect on the live corridors. Partial rather than done: the NIETC authority itself remains, FERC's backstop siting jurisdiction is untouched, and no policy binding future designations was adopted.

Research log

What was searched, and what didn’t count as evidence

Research notes

The Quote addresses FERC and the new DESAS together. DOE acted; FERC did not.

#967 rides the same announcement on the DOE grid-planning-role reading.

FERC orders are not published in the Federal Register, and ferc.gov would not open for us, so any Commission order after the notices cited could not be read.

Action
restrict
Object
National Interest Electric Transmission Corridors (NIETCs)
ID
1034